The 2029 Promise: What Offshore Wind Boosters Aren’t Telling You

By Michael Phillips | MDBayNews | Energy & Environment


A pro-offshore-wind coalition has been showing up at Eastern Shore community events this summer with a table, a model turbine, and a pitch: 1.7 gigawatts of clean power, more than 13,000 jobs, and $6.3 billion in economic benefit headed for the Shore, with construction not even starting until 2029. It is a confident, specific message. It is also only part of the story.

The material, distributed by Shore Progress, a member of the Offshore Wind Alliance, tells residents the wind farm US Wind wants to build off Ocean City is on a clear, predictable track. What it does not mention is that the project spent 2025 and 2026 in a running legal fight with the federal government over the very permit that would let it be built, that it may have missed the deadline for the federal tax credits its economics depend on, and that a federal judge is weighing a motion that could send the whole approval back to square one.

Shore Progress describes itself as a nonpartisan civic organization covering Maryland’s Eastern Shore. It was formerly known as the Lower Shore Progressive Caucus, and its chair, Jared Schablein, has also been identified elsewhere as a Progressive Maryland activist. Readers weighing the group’s neutrality on this issue should know that history.

None of that means the project is dead. It has survived setbacks before. But it means the 2029 timeline handed out at community tables is less a settled fact than a best-case scenario, one that assumes a federal court fight resolves favorably and a tax credit question gets sorted out in the developer’s favor. MDBayNews takes both sides at their word when the record supports it. Here, the record is messier than the pitch.

The coalition behind the message

The Offshore Wind Alliance is not a single group. It is a coalition that includes the Chesapeake Climate Action Network, the Sierra Club’s Maryland chapter, the Maryland League of Conservation Voters, several building-trades unions including IBEW Local 24 and Ironworkers Local 5, the BlueGreen Alliance, Shore Progress, and Oceantic Network, the national trade association for the offshore wind industry. Maryland Del. Lorig Charkoudian, a Montgomery County Democrat and the legislature’s lead sponsor on offshore wind policy, helped organize it after the Trump administration moved to unwind the project’s federal approval.

That mix matters for how readers should weigh the messaging. This is not a spontaneous grassroots movement with no stake in the outcome, and it is not simply industry astroturf either. It is a coordinated advocacy campaign built from labor unions who want the construction jobs, environmental groups who want the emissions reductions, and the wind industry’s own trade group, which has a direct financial interest in the project moving forward. Readers deciding how much weight to give the coalition’s numbers should know who is standing behind them.

Shore Progress has also sponsored its own polling on the subject, telling a local outlet in August 2025 that a survey it commissioned found majority support for offshore wind on the Eastern Shore. That is worth noting as context, not as a knock. Advocacy groups commissioning favorable polls is common practice on both sides of this fight, but it is not independent polling, and readers should treat it accordingly.

The specific figures on Shore Progress’s outreach material, the 1.7 GW capacity, the 13,600 jobs, and the $6.3 billion figure, could not be independently verified against BOEM, US Wind, or Maryland Energy Administration data. The 1.7 GW number appears to track a July 2025 rebid application US Wind filed with the Maryland Public Service Commission for 1,710 megawatts of offshore wind, a smaller figure than the 2.2 GW, 114-turbine project BOEM originally approved. The job and dollar figures do not match any public BOEM, state, or US Wind estimate MDBayNews could locate. Readers should treat them as the coalition’s own projections rather than confirmed government figures.

A permit that keeps getting fought over

US Wind’s Maryland Offshore Wind project has a long paper trail. Ocean City, Worcester County and more than 30 co-plaintiffs sued in October 2024 to block the federal approval underlying the project, arguing it would hurt tourism, fishing and coastal wildlife. BOEM issued the project’s formal Construction and Operations Plan approval, the key federal permit, that December, under the outgoing Biden administration.

Then the politics flipped. After President Trump ordered a review of federally permitted wind projects in January 2025, the Department of Justice reversed the government’s own position and asked the court to send the permit back to BOEM for reconsideration, and potentially to vacate it outright. The stated reasons: federal regulators, DOJ argued, had not adequately weighed the project’s effect on helicopter search-and-rescue operations and commercial fishing.

What has happened since, in brief:

  • December 2025: U.S. District Judge Stephanie Gallagher declined to grant US Wind a preliminary injunction that would have blocked the government from acting against the permit.
  • February 2026: Gallagher dismissed US Wind’s own counterclaim against the federal government in its entirety, ruling the administration had not yet taken a “final” action the company could legally challenge.
  • April 2026: Ocean City and its co-plaintiffs filed for summary judgment, asking Gallagher to void BOEM’s approval without a trial.
  • This summer: The federal government asked for more time to respond, pointing to a related offshore wind case in Massachusetts. Legal analysts tracking the litigation say briefing was expected to wrap up this month.

Separately, on a different legal front, the Delaware Supreme Court ruled in May 2026 to uphold state permits for the project’s onshore cable and substation work, a win for US Wind that overrode local objections from Sussex County. That ruling cleared one obstacle. The federal court fight, the one that determines whether the underlying construction permit survives, remains unresolved as of this writing.

The tax credit clock

There is a second complication the outreach table does not mention. The 2025 federal tax law, the One Big Beautiful Bill Act, cut short the runway for wind and solar tax credits. Under Treasury guidance issued after the law passed, wind projects that had not begun construction by July 4, 2026, must be fully operational by the end of 2027 to qualify for any credit at all, a near-impossible timeline for an offshore project of this size. Projects that started construction before that date get a longer runway, into 2030.

Whether US Wind’s Maryland project cleared that bar is not publicly confirmed. Energy analysts who track offshore wind financing had said for months that the shortened deadline was likely to complicate, if not kill, the project’s ability to claim the credit, given that offshore installation was not expected to begin until 2028 under the developer’s own pre-litigation schedule. US Wind has not published a construction-start announcement, and MDBayNews could not independently confirm whether qualifying physical work occurred before the deadline. That is a meaningful unknown for a project whose economics were built around a 30 percent federal cost offset.

What the 2029 date actually refers to

The “2029” figure circulating in community outreach appears to trace back to earlier reporting that described 2029 as the target date for completing the first phase of construction, not the date construction would begin. Onshore work had been expected to start as early as 2026, with offshore turbine installation following in 2028. Given the litigation timeline and the unresolved tax credit question, even that completion date is now uncertain. One energy trade publication described the project in July 2025 as likely to still be tied up in court by the time a new president is inaugurated in January 2029, a dry observation on how long the legal fight could run.

The other side of the ledger

None of this means the critics have the full picture right either. Supporters, including Sen. Chris Van Hollen and U.S. Rep. Johnny Olszewski, argue the project would create hundreds of union construction jobs and add power supply at a moment when Maryland electricity demand, driven partly by data centers, is climbing faster than new generation is coming online. Maryland Energy Administration data show the state’s approved offshore wind capacity, across multiple projects, is tied to thousands of projected construction-phase jobs and hundreds of millions of dollars in in-state spending commitments, figures that predate the current legal fight but are independently documented by the state.

Ocean City and Worcester County counter that the litigation reflects legitimate, unresolved legal questions, not manufactured obstruction, and that the town has raised the same environmental and economic concerns for close to a decade.

Bottom line

Both sides are working from real numbers. The dispute is which numbers, and which timeline, are still operative. A community outreach table that tells Shore residents the project’s scale and schedule are settled is presenting one possible outcome as the only outcome. The federal docket says otherwise, for now.


Sources: This article draws on court filings and reporting from Maryland Matters, The Daily Record, Capital News Service, WBOC, Utility Dive, Canary Media, Inside Climate News, Spotlight Delaware, the Ocean City Today-Dispatch, the Bureau of Ocean Energy Management, the U.S. Department of the Interior, Oceantic Network, the Chesapeake Climate Action Network, and the Maryland Energy Administration, along with tax guidance from the IRS, U.S. Treasury and legal analysis published by Legal Planet. Community outreach materials referenced in this article were provided to MDBayNews and could not be independently verified against government or developer data; that is noted where relevant.


Keep MDBayNews Reporting Free

MDBayNews exists to help Marylanders understand decisions made by state and local leaders — especially when those decisions affect daily life, rights, and public services.

If this article helped clarify what’s happening or why it matters, reader support makes it possible to keep publishing clear, independent reporting like this.

👉 Support Local Journalism

Have a tip or documents to share?

We review submissions carefully and confidentially. Anonymous tips are welcome when appropriate.

 👉 Submit a Tip


Discover more from Maryland Bay News

Subscribe to get the latest posts sent to your email.

Leave a Reply